What is the estimated cost of the project?

The overall project budget is currently estimated to be around $7.68 million.

The preliminary cost estimates, followed by recommended funding sources, include:

  • “Other” improvements, including streetscaping/landscaping, medians, new lighting/electrical, bicycle lanes, bridge enhancements, roundabout, tape striping, additional green space, $2,700,000 - second penny, highway bridge, loan and/or bond
  • Storm and/or sanitary sewer improvements, $1,100,000 from sewer enterprise funds
  • Storm sewer improvements, $275,000 from hydro funds
  • Street improvements, looking at the required rehabbing/reconstruction of the current roadway, $3,000,000 - second penny, highway bridge, loan and/or bond
  • Water improvements, $605,000 from water enterprise funds

Show All Answers

1. What are bicycle lanes?
2. How will the new design affect snow removal?
3. What is the estimated cost of the project?
4. What is the Tax-Increment Financing (TIF) district for project amenities?
5. What is the project phasing?
6. Why 4-Lane to 3-Lane Conversion?
7. Why a roundabout?