Green Acres Tank Waterline Distribution Project

Request email notification when page changes E-Notify

Project Information:
This project is identified within the City's Water Master Plan. New 12" water distribution line from Green Acres Tanks to 12" main along Colorado Blvd. Alignment is along 32nd Street-10th Ave-33rd Street. Also included in the project, is a new 12" line along the west side of Maitland Road that will loop the 12" Colorado Blvd water main to a 6" line approximately 1300' to the south. AE2S is the design consultant, and GTI was awarded the project at the 4/16 City Council Meeting. Construction will begin in late June, starting along Colorado Blvd and working south to 4th Avenue/32nd Street.

Public Information Meeting Presentation